Fall 2003 Schedule
As of August 29, 2003

Job Completed By Contact Person
Shower detector stacking September 20-30 Ashot
Plug in PMTs and LMS October 15 Vladimir, Samuel
Complete HyCal frame October 15 Dave Kashy
Temperature Control October 15 Yar
Data acquisition
  • Analog electronics
  • Fast electronics
  • High voltage
  • October 20 Dave Lawrence
    Eric
    Yar
    Motion Control October 20 Mark
    Abdellah
    Start HyCal cosmic test November 5 Raphael
    Dustin
    Disassemble HyCal December 10 Everyone