Job | Completed By | Contact Person |
---|---|---|
Shower detector stacking | September 20-30 | Ashot |
Plug in PMTs and LMS | October 15 | Vladimir, Samuel |
Complete HyCal frame | October 15 | Dave Kashy |
Temperature Control | October 15 | Yar |
Data acquisition |
October 20 | Dave Lawrence Eric Yar |
Motion Control | October 20 | Mark Abdellah |
Start HyCal cosmic test | November 5 | Raphael Dustin |
Disassemble HyCal | December 10 | Everyone |